Days We Have Been Ready To Build & ATG’s Lies


The situation so far…

Days We Have Been Ready To Build...

So 52 days ready to build and no money to pay for anything. Nada. Zilch.

Specifics are as follows;

Build caves – told Production 7 weeks and 3 days ago we were ready to build. Submitted quote for scaffolding. Scaffolding is needed to build the platforms the caves will sit on. Until we have scaffolding, we cannot begin building the caves. After 52 days, still no scaffolding.

Build rocket launch control room – told Production 7 weeks and 3 days ago we were ready to build. Submitted quote for scaffolding (the same quote as the caves as it was all part of one quote). Until we have scaffolding, we cannot build the ‘RLCR’ because it is needed to build the roof which needs to go in first. After 52 weeks, still no scaffolding. By the way — here’s the design for the RCLR.

Rocket Launch Control Room - 1st Floor (Emergency Mode) - 02 Nov 2015

Rocket Launch Control Room – 1st Floor (Emergency Mode) – 02 Nov 2015

Rocket Launch Control Room - Grd Floor (Emergency Mode) - 02 Nov 2015

Rocket Launch Control Room – Grd Floor (Emergency Mode) – 02 Nov 2015

Buses – we need five buses modified to look new and to be suitable for crashing. We had a contractor lined up to do the work. We were told it would take them about six weeks ago. We submitted their quote to Production five weeks ago. They promised to action it immediately. They didn’t. We still have no buses.

Buy Patrol Wagon vehicles – we need two. Production told us they will be bought tomorrow. That was four weeks ago. That’s a lot of tomorrows.

Oasis – Maysaa did a ton of work to get the quote and scope of works ready in time (totally professional as she is a full-qualified architect). Ahmed promised it would be approved by the end of the week. That was three weeks ago. It still has not been approved.

Range Rovers – this is priceless. Literally. Ahmed wants two Range Rovers so he can crash one of them. Total cost just under $250K. This despite the fact the pilot episode Art Dept budget should really be $500K. He said we would get them through Product Placement. That was five weeks ago. Fadi – head of PP – has been emailed by Ray around 10 times about this over the last four weeks. Total number of replies. Zero. Nada. Zilch.

Since arriving in Qatar, ATP has been emphasizing how we are all a team. And yet I have heard from numerous sources that despite the fact ATP has provided us with zero funds to build anything, they have been quietly blaming the Art Dept for not building anything. Even Ahmed has been extremely abusive about the Art Dept.

The only money we have had access to is petty cash which has had to come out of Majid’s own bank account. That’s right. ATP has no legal or financial presence in Qatar — even now — so it depends upon passing petty cash through an employee to pay for trinkets!!! (Is this further proof they are embezzling funds???)

This all seems to reinforce the rumour that ATP has no intention of shooting in Qatar. That it is doing whatever it can to force the shoot back to Jordan. And that it will blame anyone it can (easiest target — Art Dept) to achieve this goal.

What it does not explain is Ahmed. Why is he also blaming the Art Dept? Is he stupid? Is he in on whatever ATP is up to? Has he an alternate plan? Whatever it is, alienating the Art Dept is achieving nothing.

I had a chat with (local unnamed crew member) yesterday. He was appalled about what is going on. He reminded me of a site meeting a few weeks ago about the buses where Ibrahim promised to take responsibility for the buses after our contractor pulled out due to their having been messed about too much by ATP. He made the promise in front of Azmi, Ray, Rita, Hamad, myself, and several other people. When I wrote an email of the minutes of this site meeting, he denied saying it. Everyone was appalled by his bald-faced lie but (local unnamed crew member) was livid. He said that is when it sank in what a complete liar Ibrahim is.